All Systems Operational

Connectivity




Operational

Power




Operational

Environment




Operational

Other Systems and Services




Operational

Cloud Services




Operational

Infrastructure as a Service




Operational

External Services

MS Office365

Scheduled Maintenance

Schedule

April 7, 2025 06:00 - 09:00 CEST

Components

Power

Locations

MTH-R1, MTH-R2, MTH-R3

Description

BMIT Technologies plc shall be performing MTH On-load generator testing as per the below schedule. Schedule: Start: 07/04/2025 - 06:00 CEST End: 07/04/2025 - 09:00 CEST BMIT Technologies plc shall be closely monitoring progress during this maintenance and will keep you informed of development or prior to taking any required action. BMIT Technologies plc performs maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

April 7, 2025 08:00 - 12:00 CEST

Components

Power

Locations

MTS-R1

Description

BMIT Technologies plc shall be performing MTS On-load generator testing as per the below schedule. Schedule: Start: 07/04/2025 - 08:00 CEST End: 07/04/2025 - 12:00 CEST BMIT Technologies plc shall closely monitor progress during this maintenance and will keep you informed of development or prior to taking any required action. BMIT Technologies plc performs maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

April 9, 2025 08:00 - 13:00 CEST

Components

Connectivity

Locations

MIX

Description

BMIT Technologies plc has just been informed by one of its local carriers (GO plc) of scheduled maintenance on their local network infrastructure as per the schedule below. Schedule: Start: 09/04/2025 - 08:00 CEST End: 09/04/2025 - 13:00 CEST BMIT Technologies plc is not expecting these works to be service-affecting. However, during this period, customers might experience increased latency for traffic within Malta when this is re-routed to their redundant routes. BMIT Technologies plc performs maintenance to continue to deliver optimal performance, reliability, and security. We strive to perform them without impact on our customers' however, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

April 9, 2025 08:30 - April 11, 2025 16:30 CEST

Components

Infrastructure as a Service

Locations

Microsoft Azure Stack

Description

BMIT Technologies plc will be performing scheduled work on its Microsoft Azure Stack infrastructure as per the schedule below. Schedule: Start: 09/04/2025 - 08:30 CEST End: 11/04/2025 - 16:30 CEST The maintenance involves each Azure Stack infrastructure VM being placed in maintenance and restarted. After each restart, there might be some reconnection that experiences performance degradation. BMIT Technologies plc shall be closely monitoring progress during this maintenance and will keep you informed of development or prior to taking any required action. BMIT Technologies plc performs maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

April 10, 2025 08:00 - 13:00 CEST

Components

Connectivity

Locations

Intra-Site

Description

BMIT Technologies, together with one of its local carriers (GO Plc), shall be performing a scheduled maintenance on one of its site-to-site links between Malta, Handaq [MTH], and Malta, Smart City [MTS], as per the below schedule. Start: 10/04/2025 - 08:00 CEST End: 10/04/2025 - 13:00 CEST BMIT Technologies is not expecting that such works will be service disruptive, however, during this period, infrastructure will be running with reduced resilience. BMIT Technologies plc will be directly contacting the customers who will be directly affected with further information. Our Support is available to provide up-to-date status information or additional details, should you have any questions during the maintenance. BMIT Technologies perform maintenance to continue to deliver optimal performance, reliability, and security. We strive to perform them without impact on our customers' however, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

April 14, 2025 08:00 - April 15, 2025 20:00 CEST

Components

Power

Locations

MTH-R3

Description

BMIT Technologies shall perform scheduled maintenance on the UPS units of MTH-R3 over two [2] days as per the schedule below. Schedule: Start: 14/04/2025 - 08:00 CEST End: 15/04/2025 - 22:00 CEST BMIT Technologies plc shall be closely monitoring progress during this maintenance and will keep you informed of development or prior to taking any required action. BMIT Technologies plc performs maintenance to continue to deliver optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

April 15, 2025 02:00 - 07:00 CEST

Components

Connectivity

Locations

Arelion, Colt, International, Intra-Site, epic, MTH Switching Fabric, MIX

Description

BMIT Technologies plc will perform essential works on one of its MTH core routers as part of its commitment to enhancing performance and reliability. This activity will involve router software upgrades. Schedule: Start: 15/04/2025, 02:00 CEST End: 15/04/2025, 07:00 CEST BMIT Technologies is expecting that during this period, core infrastructure will be running with reduced resilience. Impact: - Clients with MTH circuits starting with identifier [IPB01] will temporarily lose router redundancy, with a few seconds of packet loss as traffic is rerouted. - L2VPN / BGP and associated interfaces on this router will experience multiple extended outages. Affected customers will be contacted directly with further details. Our Support is available to provide up-to-date status information or additional details, should you have any questions during the maintenance. We perform maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impacting our customers. However, a maintenance event can always have unintended consequences, up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.